Planning an infrastructure migration: a step-by-step checklist

Most migration problems come from something nobody listed: a scheduled task, a hard-coded IP, a certificate that expires on the new server. The steps below are about finding those before the cutover.

Updated 2026-10-19

1. Inventory

  • List every server, application and data set in scope, with its size, its owner and who uses it.
  • Note licences that are tied to hardware, to a host or to a region.

2. Dependencies

  • Find what talks to what: databases, file shares, printers, APIs, DNS names and anything with a hard-coded IP address.
  • Look for the hidden parts: scheduled tasks, service accounts, certificates, firewall rules and integrations set up years ago.

3. Target and approach

  • Choose, for each workload, whether it moves as it is, gets updated on the way, or is replaced (for example a file server by SharePoint).
  • Size the target from measured use, not from the old hardware’s specs.

4. Downtime and success

  • Agree on the downtime window and how much data change is acceptable to lose, if any.
  • Write down what “done” means: the checks that must pass, and who signs them off.

5. Pilot

  • Move something small and low-risk first, with real users, and time each step. The pilot is where the runbook gets corrected.

6. Rollback plan

  • Decide how you go back and, just as important, the time by which you decide. A rollback that starts too late can’t finish inside the window.
  • Keep the source untouched until the target is validated.

7. Before the cutover

  • Lower DNS TTLs a few days before, so the change takes effect quickly.
  • Take a fresh, tested backup and freeze changes on the source.
  • Tell users what will happen, when, and who to contact.

8. Cutover

  • Follow a written runbook: each step, its owner and its expected time. Sync the last changes, switch DNS or connections, and keep notes as you go.

9. Validate

  • Have the application owners run their checks, not only IT. Watch logs, monitoring and helpdesk tickets for the first days.

10. After

  • Keep the old environment read-only for an agreed period, then decommission it and wipe the data.
  • Update the documentation and, in the cloud, review the first month’s costs against the estimate.